ST-50/55 - Air Chuck Ready - Installation

Applies to machines built from: 
August, 2016

ST-50/55 - Air Chuck Ready - Installation

This procedure tells you where to make the connections to install a third-party supplied air chuck system. The air chuck must be installed by the third-party supplier.

Machine Compatibility

Do this procedure on an ST-50 or ST-55 that has the Air Chuck Ready option installed.

Step 1

Remove the coiled bulkhead air supply hoses from the storage bin.

Mount the filter, regulator, lubricator, timers, etc, from the 3rd party air chuck in the storage bin.

Step 2

Connect the air chuck hoses to the bulkhead:
  • [1] front chuck
  • [2] rear chuck

Connect the electrical components [3] of the air chuck system.

Be aware: Many service and repair procedures should be done only by authorized personnel. The service technicians at your Haas Factory Outlet (HFO) have the training, experience, and are certified to do these tasks safely and correctly. You should not do machine repair or service procedures unless you are qualified and knowledgeable about the processes.